Pipe Stress Analysis for Production Flowlines

Pipe Stress Analysis for Piping on Wellhead Flowlines have some notices as below:

·        Wellhead displacements shall be taken into account of Pipe Stress Analysis.

·        Forces due to slug flow shall be considered in the analysis.

·        Spring supports shall be considered to apply.

·        Fatigue calculations shall be carried out for a design life.

·        Pay attention to the impacts of FIV.

·        Leakage check for API Flange or Hub leakage clamp connectors

·        The scenarios calculation shall be considered in the analysis.

·        Height of shoe guides/ stops will be indicated clearly.

 

 